FG Joint Committee express delight over NEPZA Project Inspection

0
415

The Joint Projects Monitoring Committee that comprised officials from the Ministry of Industry, Trade & Investment and the Nigeria Export Processing Zones Authority (NEPZA) has rounded-off scheduled inspections of 112 approved projects for the Authority. These projects, captured under the NEPZA Tender Board of 2017-2021, direct Federal Executive Council approval and the Ministerial Tender Board of Capital Projects are located at Calabar Free Trade Zone (CFTZ), Kano Free Trade Zones (KFTZ) and the newly approved Lagos and Kwara Special Economic Zones respectively.

This is contained in a statement signed by Head, Corporate Communications, NEPZA Martins Odeh, the statement reels out that, Out of the 112 ongoing projects, a total of 76 have been completed with the CFTZ accounting for 28; KFTZ 38; Lekki SEZ 5; and Ilorin SEZ 5 while others are at different levels of completion. Some of the projects include: “Erosion Control Works & Rehabilitation of Collapsed Perimeter Fence at CFTZ; Construction of Emergency Exit Gates & Access Road to the Jetties at CFTZ; Re-Asphalting of the Exiting Dual Carriageway Road Network at CTFZ; Consulting Services for Masterplan & Architectural Design at Kwara SEZ; Consulting Services for Engineering & Infrastructure Design at Kwara SEZ; Quantity Surveying for Feasibility Studies at Kwara SEZ; and the Development of initial 5MW Power Plant & Electrical Reticulation within the Ilorin SEZ.”

“They also include: The Construction of Roads with Associated Drainage Work at KFTZ; Construction of Four Standard Size Factory Building & Associated External Works at KFTZ; The Purchase of Property at No.38 Kofo Abayomi Street, Victoria Island, Lagos; The Re-furbishing & Furnishing of the newly acquired NEPZA new Lagos Zonal Office among others.” Speaking at the end of the tour in Calabar, Director of Monitoring & Compliance, NEPZA Hajia Zainab Aliyu, expressed satisfaction with the level of projects execution across the four zones, adding that the Federal Government had always ensured value-for-money in the execution of its contracts.

Hajia Aliyu, the Authority’s Team Leader, says, the approval for the projects’ inspection tours indicated government priority toward adequate provision of infrastructure in the free trade zones and Prof. Adesoji Adesugba led-management relentless commitment to the interpretation of President Muhammadu Buhari’s policy for a profitable and competitive zone scheme.

“As part of the statutory responsibility of NEPZA as provided in Section 4 of the Authority’s Act 63 of 1992 is the provision that ensures that all zones provide some of the basic infrastructure. We are also obliged to constantly monitor and evaluate both new and old infrastructure. “The reasons for these monitoring and evaluation exercises were to ensure the right quality of materials were used and the right quality of jobs are done, just as we also checked the percentage of work done in line with the amount assigned for the project. “To this end, the Managing Director, Prof. Adesoji Adesugba decided to set up this committee to access all the projects that have been earmarked from the period he assumed leadership of the Authority.